HESS

Client’s Requirement:

·   Asset Register & Equipment Lists

a.     Creating asset register inclusive but not limited to P&IDs, non-P&ID items, ex-equipment register, lifting equipment register, special tools & testing equipment list.

b.     Validate and update the asset register master

·   Develop the Risk Matrix & Integrity Critical Element (ICE) Register.

·   Develop Performance standards for equipment/asset with appropriate pass/fail criteria where it is applicable.

·   Develop maintenance Plans, Items, Task Lists, Task List Operations and where required, materials required for task.

·   Preparation of Material master for catalogued items.

·   Develop BOM (Bill of Material) in accordance with required method

EDMS-K2 provided a team on site using our proprietary tools and methodologies to:

·   The hierarchy was developed and grouped using engineering code and system

·   philosophy in liaison and approval from the SKHL. This was approach was later

·   altered based on the commissioning marked-up P&IDs and client specific requirements.

·   The ICE assessment workshop was completed and the review focus safety system, environmental and production.

·   Performance Standard for assets with ICE rating A to D was then developed upon

·   completion of the ICE register and with appropriate client approval.

·   Maintenance data was compiled in the form of plan, items and task lists with

·   respect to SAP/PM Master Standards document.

·   K2 compiled project specific spares & BoM data and submitted a template based on similar project knowledge and experience, for client to use as required.

 

Benefits & ROI:

·   Utilized ADAM software to provide the advanced data capture and analysis required for the development of an effective EAM (CMMS) system, ensuring high-quality, error-free data in a format suitable for upload to SAP.